Thursday, July 28, 2005

Dredging Project Monitoring

Dredging/Disilting update as of 7:30am 27 Aug 2005

Numberof truckloads hauled from Sta rita River to Olongapo Landfill
24 Aug: 6 loads
25 Aug: 8 loads
26 Aug: 30 loads
Image Hosted by ImageShack.usImage Hosted by ImageShack.usImage Hosted by ImageShack.us

Monday, July 25, 2005

Dredging of Sta Rita River


Image Hosted by ImageShack.us
Dredging projects to rehabilitate the city's river system started today at Sta Rita River.

Image Hosted by ImageShack.us
Dredging for another part of the city's river system will start anytime next week at Kalaklan River. This project awarded to R.M. VITUG Cosntruction cost P20,000.000 w/ total volume of material to be dredged estimated at 125,775 Cu.M.

Image Hosted by ImageShack.us
The project was awarded to R.D. SADSAD Construction from Angeles City. 63,000 Cu.M. of sand and silt is expected to be excavated in this project which cost P10,000,000.

Image Hosted by ImageShack.us


Image Hosted by ImageShack.us
The desilted materials are brought to the city's landfill in accordance with the City Ordinance authored by Councilor Edwin Piano. This will ensure ample supply of topsoil neccessary to maintain the sanitary landfill.

Image Hosted by ImageShack.us


Photos Below were taken to document the "before and after" impression of the project

Image Hosted by ImageShack.us